Carefree Azusa Update- paint for Phase 1 and 2

Phase 1 update: all of the damaged wood repair has been replaced. We will be finished with the painting in this phase by the end of today. (Streets Pebble Beach, Indian Dunes and Hermitage) We are finishing up the last building on Hermitage right now.

Phase 2 update: notices were posted for the starting of the painting at units 303/311/319/327 and 335/343/351 Annandale. We will be working on painting these two buildings once Hermitage is finished. We will be back to work on Tuesday to start the painting of the rest of the buildings in phase 2.

Phase 3: prep work will be starting on Tuesday Sept 2nd.