Client Updates Center

Client Update

UHCCCA- Upland Hills Dr. North update

On Thursday August 22 we are going to be starting the high pressure cleaning of the units along Upland Hills Dr. North. The high pressure cleaning will take 2-3 days. After the high pressure cleaning we will start working on the wood replacement (week of August 26-30th- pending board approval of wood). The painting will start the week of September 3-6th. (Labor Day is Monday September 2nd and we will not be working in the community). For the painting project we will be working in color scheme number order ie: all units in color scheme #1, all in #2 etc.

 

If you have any questions please do not hesitate to call the office at 909-980-4059 or talk to our foreman onsite (Carlos wearing the red shirt).

For questions, concerns or comments, please email us here

or call us at 909-980-4059.