Client Updates Center

Client Update

Montclair Town Homes- update

The high pressure cleaning of the units in phase #1 has been completed.

Wood Repair: we will be starting to remove and replace the damaged wood tomorrow. 4/23

Prep work: today we are working on patching stucco & priming siding and eaves. We are prepping the following units: 10474, 10472, 10478, 10476, 1046410462, 10468, 10466, 4536, 4534, 4538, 4532.

Please refer to prior post if you would like to know what Painting Phase your unit is in.

For questions, concerns or comments, please email us here