Amador Update: 17,18,19,20,21
Buildings 17 & 18 are done (we will be back to paint the doors and shutters)
Building #19- we are working on painting the trim righ now, the eaves have been sprayed.
Building #20- the eaves have been sprayed, we will be working on the trim after the trim on number 19 is done.
Building #21- we are spraying the eaves right now. The trim is not done yet.