Amador- 17,18,19 update
Building #17: The spraying is finished, we are currently working on painting the trim.
Building #18: The spraying is finished, we need to do the trim.
Building #19: We are working on spraying the eaves today.
Building #17: The spraying is finished, we are currently working on painting the trim.
Building #18: The spraying is finished, we need to do the trim.
Building #19: We are working on spraying the eaves today.