Waddell Painting and General Contracting is happy to bring our clients our all new "Client Updates Center". We have embraced new technology that will make checking your current project for updates. We understand the value of efficiency and hope you find this added service as a value.

Recent Client Updates

  • UNDER CONSTRUCTION

    We are currently updating our website and Client Update Center

  • Carefree Fence Update

    Notices are being posted for the fence removal and replacement for the following Buildings: 333 Hermitage Fence will be started Monday January 5th 352 Hermitage Fence will be started Monday January 5th

  • UHCCCA- update

    We will not be working onsite today due to the wet weather. We hope you have a happy and safe Memorial Day Weekend.

  • UHCCCA- update

    Today we started painting the stucco in color scheme #5. Tomorrow we will be starting to paint the trim. We will be starting the trim painting up at the North End of Pebble Beach.

  • U.H.C.C.C.A update

    As of today color schemes #1 and 2 are done having the stucco and garage doors painted. We will be back to paint the trim and front doors. We are working on painting the stucco for scheme #3.  Buildings 816/820/824/828 and 720/724/728, 732 Pebble Beach have had their stucco painted. Today we starting painting at […]

  • UHCCCA Rain Delay

    We will not be working on site today due to the rain. We will be back onsite when the weather dries up.

  • UHCCCA- update

    We finished the high pressure cleaning last week. Today we are working on the “prep work”. Prep work includes patching stucco, caulking etc.  Today we are prepping on St. Andrews street. Tomorrow we are planning on starting to paint the main stucco body of units in color scheme #1. Starting at 800/804/806/812 Pebble Beach and […]

  • Upland Hills Country Club Condo Assocation 2015 Project- color scheme & start date

    The 2015 painting project phase will begin on Monday April 20th. This phase will include the following (57) units. Color Schemes: (Vista Paint) Scheme #1: Body- 72 Togo Garage Doors and Front Doors- 43 Sand Pebble Trim- 59 Bone White   Scheme #2: Body- 8457 Bamboo Beach Garage Doors and Front Doors- 97 Mesquite Trim- […]

  • Upland Hills Estates- front door painting

    Just a reminder that we will be painting the front doors this Saturday April 11th. Please call our office if you need to request a specific time. 909-980-4059

  • Upland Hills Estates

    You will be receiving a notice for the painting of the front doors. We have them scheduled for Saturday April 11, 2015. Please contact our office if you need to schedule a specific time. 909-980-4059> Note: the doors will need to be left open 2-3 hours to dry before you can close them.

  • Upland Hills Estates update

    Today we are working on painting the stucco in scheme #8. Tomorrow we will be starting the prep work for the homes in color scheme #10. We should be starting to paint the stucco on homes in color scheme #10 on Friday. Next week we will be working on painting finishing up scheme #10 and then […]

  • Upland Hills Estates- Scheme #3

    The painting of the body/stucco color for scheme #3 is starting today. We will be back to paint the trim, doors and gates after all of the stucco is painted for all color schemes.

  • Upland Hills Estates: scheme #1

    The painting of the body/stucco color for color scheme #1 is finishing up today. We will be back to paint the trim, doors and gates after all of the houses have had their stucco painted.

  • Upland Hills Estates- Painting of the body/stucco color in scheme #1

    The painting of the body/stucco color in scheme #1 is starting today.

  • Upland Hills Estates- Prep work starting

    The prep work is starting on units in color scheme #1 and color scheme #3.

  • Upland Hills Estates- High Pressure Washing

    The high pressure washing will be completed today for all of the homes in the project.

  • Upland Hills Estates- High Pressure Cleaning

    High pressure cleaning is starting today. Once the high pressure cleaning is done we will be prepping the buildings for paint (caulking/patching etc), then we will be painting the main body stucco color and popouts for each unit- working in color scheme number order, after the stucco is painted we will come back through to […]

  • Upland Hills Estates 2015 Color Schemes

    Address:     Color Scheme # 1318-1322     6 1328-1332     5 1336-1340     8 1334-1348     4 1352-1356     1 1360-1368     10 1374-1380     3 1382-1386     6 1394-1398     5 1404-1408     8 1415-1421     10 1418-1422     4 1426-1432     1 1427-1433     8 1434-1438     10 1442-1444     3 1443-1449     1 1452-1456     6 1455-1463     4 1460-1464     5 1465-1471     3 1470-1474     8 Scheme #1: Stucco (main body): Drifting DEC […]

  • Upland Hills Estates 2015 Painting Project

    The 2015 Painting Project will be starting on Monday March 2, 2015. Notices have been posted. Please make sure to call Natalie at our office 909-980-4059 to report your front door and gate color selections. Please note: you will receive a high pressure washing start notice.

  • Carefree Azusa Fences

    307 Indian Dunes (Front 13′ fence) and 321-327 Cherry Hills (Front 6′ divider fence): will be started tomorrow 1/28/15. We will remove the existing wooden fences and replace with Hardi panel cement fencing. This project is estimated to take 2-3 days to complete.

  • Carefree Azusa update

    The fencing in this phase of the project have been installed. We will be painting the new fences today and then we will be done.

  • Turnbull Canyon – update

    We have finished the removal and replacement of damaged wood for this project phase.

  • Bon View Next Painting Phase

    Building 2044, 2046 & 2022 Notices are being posted today to start this phase of the painting project on Monday January 12th.  

  • Turnbull Canyon Update

    Notices were posted Friday January 2nd, stating that we will be starting the wood removal and replacements in the backyards today January 7th.

  • Glendora Woods Power Washing 979-985

    Today we high pressure cleaned units 979, 981, 983 and 985. Prep work will continue tomorrow **weather permitting.

  • Turnbull Canyon Update

    Today we were able to finish up the wood repairs for everything except the backyard areas. We will be returning after the first of the year to complete the backyard area wood repairs.

  • Glendora Woods update

    We are working on finishing up painting the trim for units 961, 963, 965, 967. We also started the high pressure cleaning of units 969, 971, 973 & 975 yesterday. We will be prepping these units today. Note: the board approved to paint the roof vents so we will be doing everyone’s roof vents at […]

  • Turnbull Canyon update

    We will be starting the wood removal and replacement on the front and accessible sides of the units. The backyards will be scheduled for after the first of the year.

  • Turnbull Canyon

    We will be starting the wood removal and replacement for the following units on Monday December 8th (weather permitting). 15202 Shadybend Units 17-22 and 15228 Shadybend Units 12-16. Notices are being posted today for those homeowners. Please make sure gates are not locked, all windows are closed; valuables and breakables should be placed out of […]

  • Glendora Woods- Rain delay

    We are not painting on site today due to the rain. We will be back once the weather clears up.

  • Montclair Town Homes

    This phase of the project is now complete.

  • Montclair Town Homes- weather delay

    We are not working on site today due to the windy weather.

  • Glendora Woods- Rain Delay

    We are not working on site today due to the rain. (The stucco is to wet to paint). We will be back Monday **weather permitting.

  • Montclair Town Homes- Update

    Today we are working on painting the trim and fascia on the 10493/10495/10497/10499 Adobe Ct building. We are also working on damaged wood replacement.

  • Glendora Woods update

    Friday we started the high pressure washing of 945, 947, 949 & 951 Shady Ln. We are working on prepping those units today. Painting will follow the prep work.

  • Glendora Woods Update

    Units 927/929/931/933: today we are painting the stucco and siding. Tomorrow we will be painting the eaves. Friday we will be painting the trim. Units: 935/937/941/943: we will be posting the pressure washing notices today or tomorrow. It’s looking like we will be high pressure cleaning the units on Monday 11/10.

  • Montclair Town Homes

    The high pressure cleaning of the units in the phase 2 of the painting project are being high pressure washed today. This process may take a day or two to complete the units in this phase. Prep work and painting will follow.

  • Glendora Woods Update

    We put up notices last week….units 927/929/931/933 are being high pressure cleaned today. The following units are done with the painting (except for the front doors). 903/905/907/909,   911/913/915/917,   919/921/923/925 * we will be posting a front door notice within the next day or so. We will be painting the remaining edge around the face of […]

  • Glendora Woods Power Washing update

    We have notified the owners for the next four units: 919/921/923/925 that we will be high pressure cleaning their units tomorrow. Prep work is moving along nicely. 911-917 have been high pressure cleaned, prepped and are getting painted. 903-909 Are done (except front doors)

  • Montclair Town Homes

    The high pressure cleaning will start on Monday November 3rd. This next phase of the painting project includes the following (16) units: 4583/4585/4581/4587 Gold Rush Ct. 10473/10471/10477/10475 Yosemite Dr, 10483/10485/10487/10489 Adobe Ct, 10493/10495/10499/10497 Adobe Ct.

  • Glendora Woods Update

    Today we are high pressure cleaning the next set of units: 911/913, 915/917. We will then be prepping these units and painting them. Note: 903-909 are done. (Except for front doors- which will be done at the end of the painting project). The next set of units will be: 919/921, 923/925.

  • The Legends touch up update

    On this coming Saturday October 25th we will be at the association to do touch ups. If you are one of the 3 homeowners who needs to have the little edge around the front door painted…please call in so that we can schedule a time for you- or we will try to contact you on […]

  • Glendora Woods update

    Units 903/905, 907/909 update: we are done with the high pressure cleaning. Today we are prepping for paint (Prepping includes: patching, sanding/scraping, caulking etc.) Priming and painting will follow. Note: The next four units to be painted will be 911/913, 915/917. They will receive a notice prior to the high pressure washing.

  • Stonebrook Estates- update

    We are back on site today- working on wrought iron fence painting.

  • Glendora Woods- update

    All of the wood repair has been completed for the homeowners who have contracted with us to do so. Please make sure to mail in your payment or give a check to our onsite foreman. High pressure cleaning of units 903/905, 907/909 Shady Lane will be starting of Monday. Please see the previous post for […]

  • The Legends update

    As of today we are working on prepping, priming and painting the front yard decorative wrought iron. We will be working on touch up tomorrow and Friday. Saturday we will be painting the remaining edges around the front doors. If you would like  a proposal to paint your wrought iron fencing please contact our office […]

  • Glendora Woods- pressure cleaning notice

    Monday Oct 13th we will be posting high pressure cleaning notices. We will be starting the high pressure cleaning of units 903/905, 907/909 on Monday October 20th. We will high pressure clean those units, prep and then paint them. Then we will move to units 911/913, 915/917 and high pressure clean, prep and paint them. […]

  • The Legends- update

    As of right now we are done painting all of the garage doors and the centers of the front doors. Our crew is currently working on painting the fascia in color scheme #1 unit 102 Calle Rosa. We will be painting the fascia in color scheme number order.

  • Glendora Woods- wood replacement

    We have completed the damaged wood removal and replacement on the following addresses: 917, 919, 929, and we were working on 927 yesterday.

  • The Legends- Update

    Sorry for the delay in posting an update as the website server was down. Yesterday we worked on painting the front doors and the garage doors- we will be finishing them up today. We will be posting a notice stating that we will be there on Saturday October 18th to paint the remaining edge of […]

  • The Legends

    As of today we are working on painting the stucco for color scheme #4. We will be starting to paint the stucco in color scheme #5 next Tuesday or Wednesday. For color schemes # 1, 2, 3 we have painted the stucco and the popouts. We still need to paint the trim, front doors and […]

  • Glendora Woods

    This coming Monday we will be starting the removal and replacement of damaged wood for the homeowners who have contracted with us to do so. We will be working in numerical order from the low 900’s to the high 900’s. If you had your wood replaced by a different contractor please make sure that they […]

  • Glendora Woods- update

    Notices will be posted tomorrow stating that Waddell will be starting the wood replacement (for the homeowners who have contracted with us) on Monday October 6th. They also state that if you are having a different contractor replace your wood- you need to have that completed by October 20th. Please note: if you have a […]

  • Glendora Woods Update- Working Direction

    We will be working in your association from the entrance off of Sunflower (West Side) along Shady Lane going East. We will be working in numerical order of addresses.

  • The Legends- update

    Today we are working on painting the stucco for the units in color number two.   The stucco and pop-outs are painted in color #1. Tomorrow (Saturday) we will be painting the fascia for color scheme #1.   If you have any questions please feel free to ask Carlos- our foreman in the Red Shirt. […]

  • Glendora Woods -wood repair notice

    On Tuesday September 30th we will be posting a start notice for the wood replacement. The notice states that we will begin the removal and replacement of damaged wood for the homeowners who have contracted with us to do so. If you have approved for us to do the repairs- there will be an invoice attached […]

  • The Legends update

    As of right now we are working on finishing up the last building in color scheme #1 (244/252) We have finished painting the units 150/158 and 118/126 except for the stucco popouts (around the windows). We should have the stucco popouts painted by Wednesday or Thursday. After the color scheme #1 is finished we will […]

  • Carefree Azusa update

    We finished the wood replacement and the painting on the Clubhouse this past Saturday. We are now done with the painting project throughout the association.

  • The Legends- update

    We have gone through and marked all of the damaged wood with orange paint. We have submitted a proposal for approval on replacement. Today we are working on prepping the second building # 118/126.

  • Carefree Azusa- clubhouse

    Today we are working on replacing the damaged wood on the clubhouse and then we will be painting the trim. We are also working on painting fences that we recently installed.

  • The Legends- Power Wash Update

    Yesterday we were able to high pressure clean units 102-204. Today we started at 212 and should be able to finish the rest of the units up to 268.

  • The Legends Color Information

    Here is the color scheme information for the painting project: (Paint Manufacturer is Dunn Edwards)   Scheme #1: Address:118, 126, 150, 158 Body- DEC 726 Adobe Trim- DE 6195 Prarie Grove Stucco Foam- DE 6196 Milk Mustache Entry Door: DE 6196 Milk Mustache Decorative Wrought Iron: DE 6195 Prarie Grove   Scheme #2 Address: 166, […]

  • Carefree Azusa- rain delay

    We started working this morning but had to leave due to the rain. We will be back tomorrow if the weather dries up.

  • The Legends- start notice

    Start notices were posted today… *Weather Permitting* We will be starting the high pressure cleaning next Monday September 15th. We will be working from 102 towards 268 Calle Rosa- *we will not be able to finish all of the units in one day. This high pressure wash is necessary before painting can get started on […]

  • Carefree Azusa update

    As of today… Phase one has been completed. Phase two: we are working on painting on St. Andrews. We are working on replacing damaged wood on Cherry Hills. Phase Three: the prep work has been completed. Only one piece of damaged fascia was noted in this phase and will be replaced after the wood replacement […]

  • Carefree Azusa Update- paint for Phase 1 and 2

    Phase 1 update: all of the damaged wood repair has been replaced. We will be finished with the painting in this phase by the end of today. (Streets Pebble Beach, Indian Dunes and Hermitage) We are finishing up the last building on Hermitage right now. Phase 2 update: notices were posted for the starting of […]

  • Hampton Gardens Car Ports

    On Tuesday Sept 2nd we will be high pressure cleaning carports 1-26. **Do not park in those spots. On Wednesday Sept 3rd- we will be painting carports 1-26 but you can park there. We will also be high pressure cleaning carports 27-46 on Wednesday.** Do not park in those spots. On Thursday Sept 4th- we […]

  • Closed Monday September 1st

    Our office and job sites will be closed on Monday September 1st. Have a fun and safe Labor Day Weekend.

  • Carefree Azusa- Phase 3

    Starting on Tuesday September 2nd we will be working on prepping the phase 3 area. Phase 3 consists of Units on Quail Hollow and Tam O’Shanter.

  • Carefree Azusa- Phase 1 wood repair

    Today we are working on removing and replacing the damaged wood throughout phase #1. (please note: we will not be doing wood replacement in the eaves).

  • Stonebrook Estates- wrought iron

    Starting on Monday September 22, 2014 we will be painting the back wrought iron fences behind (14) lost on the map provided on the notice, the pool area wrought iron fence, the pool equipment room fence, the wrought iron fence by the tennis courts, (2) lights on Ivanpah & Sitting Bull Gates. The notice to […]

  • Carefree Azusa update

    Today we have started prepping throughout phase two of the project. (Addresses on Annandale, St. Andrews and Cherry Hills).   Notices will be posted for phase 3- which will be starting next Tuesday September 2nd. (We will not be working on Monday Sept 1st in observation of the holiday).

  • Mayflower DeVille- Front Doors

    We will be painting front doors on this Saturday August 30th. From 7am to 3:30 pm. If you need to schedule a specific time please call our office at 909-980-4059. Please note that your front door will need to be left open 2-3 hours to allow for proper drying.

  • Carefree Azusa- Phase 2 of prep work

    Monday August 25th we will be starting the prep work for phase 2 of the project. Phase 2 consists of the following streets: Annandale, St. Andrews, Cherry Hills. Reminder: prep work will be scraping, sanding and caulking as needed. High pressure cleaning will not be done as requested by the board due to drought conditions.

  • Glendora Woods- tentative timeline

    Wed August 20th: Waddell to hang visual wood inspection notices. Mon August 25th: Waddell to do visual inspection and mark damaged wood in red. By Wed August 27th: Waddell to leave bids for homeowners for damaged wood on their unit. Mon Sept 29th: Waddell to hang wood replacement start notices. Mon Oct 6th: Waddell to […]

  • Carefree Azusa- update

    All of the prep work has been completed for the phase 1 (streets- Pebble Beach, Indian Dunes and Hermitage). We will be back to start the prep work for phase 2 on Monday.

  • Mayflower DeVille- update

    As of today we are all done painting the Stucco, Siding, Garage Doors and Front Doors. We are working on painting the trim.

  • Carefree Azusa- update (Pebble Beach)

    This morning we started the prep work on 381/373/365 building on Pebble Beach. We will then move to the 357-333 Pebble Beach building, the 325-301  Pebble Beach building and then back down the other side of Pebble Beach 308-364 and then to 372/380. *All of these units will not be done with the prep work […]

  • Carefree Azusa- note on pressure cleaning

    Per the board’s request we will not be high pressure cleaning. (Concerns about using water during the drought). Instead we will be scraping and sanding. You will still need to move items away from areas that will be painted as noted in the high pressure cleaning notice.

  • Carefree Azusa- update information

    Just a quick note- we will be posting notices to keep everyone informed and updating this blog as much as possible. If you have questions you can call our office at 909-980-4059 or talk to the foreman onsite. Our foreman will be wearing a red shirt while the rest of our crew wears white.

  • Carefree Azusa- Paint Project Info

    Notices are being posted today for the upcoming painting project. The high pressure cleaning will be done in three phases. Damaged Wood will be inspected after the high pressure cleaning and then a walk will be scheduled with the board to address the wood replacement. The project will flow: high pressure cleaning, wood removal and […]

  • Countrywood Park II- fences

    This coming Saturday August 16th make sure to leave your gates unlocked. Like the notice that we posted states- we will be doing our final inspections.

  • Mayflower DeVille- colors

    The new paint colors for you association are: Sherwin Williams: Trim- 7008 Alabaster Garage/Siding- 7515 Homestead Brown Stucco- 7039 Virtual Taupe Railing/Doors- Black

  • Mayflower DeVille

    Today we are working on removing and replacing damaged wood and prepping the buildings for paint. Our crew is currently at the 1306 and 1302 building.

  • Turnbull Canyon- 15200 &15230 completion

    The removal and replacement of damaged wood for the 15200 & 15230 buildings has been completed.

  • Turnbull Canyon 15200 & 15230 Bldg

    The removal and replacement of damaged wood on the 15200 & 15230 buildings has started today.

  • Hampton Gardens- Bldg C update

    The high pressure cleaning on unit C will be started tomorrow. Wood removal and replacement will follow the high pressure cleaning.

  • Hampton Gardens Building C update

    Today we will be posting notices to start the high pressure washing of the exterior of Building C on Thursday July 10th.

  • Countrywood Park II update

    Tomorrow we will be working on touching up the stucco paint. Thursday the additional materials needed will be ready and we will be working on the final gates, touch ups etc.

  • Glendora Oaks update

    As of today we are putting the finish coat on the following units: 1230, 1222, 1216. The next set of homes have been noticed and will start tomorrow (the center units around the pool).

  • Hampton Gardens- building A Update

    Today we are finishing up the touch ups to the paint on the siding and stucco for Building A units: 1-12. We are also working on painting the centers of the doors. We will schedule/post a door notice to paint the remaining edge that can only be accessed while the door is open, at a […]

  • Hampton Gardens- update

    All of the stucco and the siding have been painted on the first building A. Tomorrow we will be working on painting the trim.

  • Glendora Oaks- update

    As of today 1230/1222/1216 units- all units have been prepped (except ones that still have bushes that need to be cut). Tomorrow we will start priming.

  • Glendora Oaks- update

    Backyard wrought iron fencing: Notices are being posted to start the following addresses on Wednesday July 2nd. (All of the center buildings). 1220, 1218, 1212, 1204, 1224. Please make sure that your bushes have been trimmed back so that we can paint your fencing.

  • Hampton Gardens- Building B start notice

    Today we are posting the start notice for Building B units: 13-24. This building will be started next Wednesday July 2, 2014. We will start with the high pressure cleaning, then wood removal and replacement, then prep work and then paint.

  • Hampton Gardens- Buidling A update

    Today we are working on wood replacement. We have also started working on painting the stucco.

  • Hampton Gardens- Building A update

    Building A: Units 1-12 All of the high pressure cleaning has been completed. Today we are working on prepping the building for paint (caulking, patching, sanding, priming areas etc..) We are also working on the damaged wood removal and replacement.

  • Hampton Gardens: Paint Color Information.

    Dunn Edwards Paint Body: DE 6374 Silver Polish Siding DE 6348 Draw Your Sword Front Door DEA 147 Garnet Evening Trim Dew 380 White    

  • Countrywood Park- Fences

    We are posting notices today to start the last five buildings on Monday. The addresses are: 1451, 1453, 1455, 1457, 1461.

  • Glendora Oaks schedule

    On Monday we will be starting at the 1230 building: working from unit F towards Unit A. Then moving to the 1222 building: unit F towards unit A. Then to the 1216 building: unit F towards unit A. The back wrought iron fence will be prepped first…sanded, wire brushed etc. and then will be painted. […]

  • UHCCCA- completion

    Completion notices will be posted today. This years painting project is close to completion. Please take a few minutes to look around your unit and note any concerns that you may have. You can email your concerns to Natalie@waddellpainting.net, call our office at 909-980-4059 or fax to 909-987-6660. We ask that you do this by […]

  • Glendora Oaks- wrought iron painting

    The wrought iron painting project is scheduled to start Monday June 23, 2014. More information to follow.

  • Azure Hills- red curbs

    We are back working on the red curb painting project. Please do not park in areas that we are working in.

  • Bon View- update

    This phase of the painting project will be completed today. Tomorrow we will be working on the final touch ups.

  • Hampton Gardens: Start Date June 23rd

    Building A: units 1-12 Starting: Monday June 23, 2014 High pressure cleaning of the building exterior. Please make sure all windows are closed, valuables and breakables should be placed out of the way, to insure there are no difficulties with the procedure. All personal items must be removed from all areas that will be painted. […]

  • UHCCCA- update

    Notices have been posted for the painting of the front door/edge painting for this coming Saturday June 14. Color schemes 1,2 & 3 had their front doors done last Saturday. This coming Saturday is for color schemes 4 &5 (but we can finish any doors in the other schemes if they were not able to […]

  • Hampton Gardens- general notice

    Notice to Homeowner: Starting Monday June 23, 2014. Waddell Painting Inc. has been contracted to paint the exterior of the homes throughout your association. We will be starting at Building A: Units 1-12, then building B: units 13-24, then building C: Units 25-46. The building will be high pressure cleaned, wood repairs will be made […]

  • Countrywood Park II -Update

    The next five buildings have been noticed and we will start removing the old fences Monday June 9th. 1468, 01464, 1460, 1480, 1476.

  • UHCCCA- front doors

    Half of the units received a notice for the painting of the front doors for tomorrow (Saturday June 7th). The other half will be noticed shortly. If you need to schedule a specific time please call our office to make arrangements. 909-980-4059. If you have requested to have a bid to paint your patio cover […]

  • Bon View

    We will be starting the painting of the stucco tomorrow 6/3.

  • UHCCCA- front doors

    A notice for painting of the front doors (or the remaining edge of front doors) will be posted tomorrow for this coming Saturday June 7th. If you need to schedule a specific time please call our office at 909-980-4059. Times can be set for between 7am and 3:30 pm.

  • Bon View update

    The high pressure cleaning has been done and now we are working on prepping the buildings for paint.

  • Countrywood Park- update

    Tomorrow the following buildings will be having gates installed: 1427, 1425, 1423, 1452, 1456. We will be starting the fence replacements at the following buildings on Monday June 2nd: 1433, 1435, 1437, 1439, 1441.

  • Azure Hills- Red Curbs

    We will be starting the painting of the red curbs throughout your association on this Thursday May 29, 2014.

  • UHCCCA- update

    On Saturday we hung up start notices for the painting of the stucco for the last color scheme #5. Some of them were for today and some of them were for tomorrow. Homes in color scheme #5 are: 827/831/835/839,   864/868/872/876,    1031/1041/1051/1061,   1151/1161/1171/1181/1191. Please note: we are going to be painting the stucco and then coming […]

  • Bon View- Buildings 2042, 2024, 2040

    We will be starting the high pressure cleaning of the units in buildings: 2042, 2024 and 2040 on Tuesday May 27th. Notices are being posted today. Preparation and painting will follow the high pressure cleaning.

  • UHCCCA- Update

    Notices were posted for the stucco painting in color scheme #5 to start yesterday. This has been placed on hold until Tuesday. We are currently working on finishing up items in the other colors schemes before we start on your homes. We will not be working at your association during this weekend or Monday to […]

  • Upland Hills Estates- Project completed

    All of the house painting, wrought iron painting, wood repair and fence replacement has been completed. It was a pleasure to work for your association again this year.

  • UHCCCA- update

    Just a note to let the homeowners know…we will not be working on site in your community this Saturday or Monday due to the Memorial Holiday. We hope you enjoy your weekend. Also, we will be posting a notice prior to starting the painting of the wood trim on units (looks like this may be […]

  • UHCCCA- update

    Here is an update on the painting project as of right now… Units in color scheme #1: all of the stucco has been completed. Trim will be started after the stucco in the others schemes has been completed. Units in color scheme #2: ( 832/836/840/844, 952/962/972/982, 1071/1081/1091/1099) we are finishing up painting the stucco on the last […]

  • UHCCCA- update

    All of the high pressure cleaning has been completed. We are now working on color scheme #1: 843/847/851/855,        945/955/965/975,          1050/1060/1070/1080/1090,      1203/1207/1211/1215

  • Countrywood Park- fence update

    This Thursday we will be installing the gates on the previously installed fencing. We will also be hanging notices to start the next 5 buildings on Monday. The Next five buildings that are being started on Monday May 5/19/14 are: 1427, 1425, 1423, 1452, 1456.

  • Upland Hills Estates-completion notice

    Please take a few minutes to look around your home to see if you would like to note any touch ups or concerns. Please call our office at 909-980-4059 if you would like to bring anything to our attention. The project has been completed along with the wrought iron painting project.

  • UHCCCA- power washing update

    As of today 5/7/14 we are done with the power washing of the following homes: 827/831/835/839, 843/847/851/855, 945/955/965/975, (North side of the street)   832/836/840/844, 848/852/856/869, 864/868/872/876, 880/884/888/892, 912/922/932/942, 952/962/972/982, 1004/1012/1020/1026 (South side of the street)   We are currently working on at the 1050 and 1021 Buildings. The high pressure cleaning should be finished […]

  • Countrywood Park – postponement

    Please note: the fencing project has been postponed and will resume next Tuesday May 5th. Sorry for any inconvenience this may have caused.

  • UHCCCA- power washing reminder

    Please make sure to have your plants/bushes trimmed back at least 6-8 inches prior to the high pressure cleaning that is going to be started on Tuesday May 6th. (Power washing got moved from Monday April 28th to Tuesday May 6 due to the wind).

  • Upland Hills Estates- update

    We are posting notices today to complete the remaining front door painting for this years painting project. We will be onsite this Saturday April 26, 2014. If you need to have the remaining edge around your door painted and would like to schedule a specific time, please call our office no later then Friday. 909-980-4059

  • Countrywood- update

    We are posting notices today… The following buildings will be started on Monday 4/28/14… 1448, 1444, 1440, 1431, 1429.

  • Upland Hills Estates- update

    We are currently working on painting the wrought iron fencing. The remaining front doors that need to be painted will be given a notice for Saturday April 26th.

  • UHCCCA- 2014 Project Notice

    The 2014 Painting Project is scheduled to start on Monday April 28, 2014. Information notices will be posted today.  We will be painting all stucco, wood, walls and doors on the homes 832 Pebble Beach through 1215 Pebble Beach. We will be working from West to East for the high pressure cleaning. (High pressure cleaning […]

  • Countrywood Update

    Notices have been posted to start the fence removal on the following (5) buildings on Monday April 14, 2014- 1440, 1444, 1448, 1431, 1429.

  • Upland Hills Estates-wrought iron painting project

    Notices will be posted for the painting of the backyard wrought iron fencing on the units in this years wrought iron fence painting project. This project will be starting on Monday April 14, 2014. Please make sure that your plants are trimmed back if you receive one of the notices. Also, if you have mesh- […]

  • Countrywood Park-fence project update

    Please do not shake the fences or the posts while the cement is curing.

  • Upland Hills Estates- front doors

    We will be posting front door notices on half of the homes in this years painting project. The notices will inform those homeowners that we will be at the association on Saturday April 12th to paint front doors. If your front door has already been painted then we will be painting the remaining edge of […]

  • Countrywood Update

    We will be starting the fence removal today on the following (5) buildings: 1420, 1424, 1428, 1432, 1436.

  • Countrywood Park Update

    Yesterday we removed the old fences at: 1409, 1421, 1419 buildings. Tomorrow we will remove the old fences at: 1417 and 1415 buildings. Next week we be removing the fences at: 1420, 1424, 1428, 1432, 1436.

  • Countrywood Park II update

    As of today: 1400, 1404, 1408, 1412, 1416, 1407 are done with gates.   1405/1403/1401/1413/1411: we will be doing clean up tomorrow. Ordered the gates and will install as soon as we receive them.   1409, 1421, 1419, 1417, 1415: we are posting notices tomorrow to start the removal process on Monday.

  • Countrywood Park II Update

    As of yesterday we have worked down the entire row of the following addresses: 1400,1404, 1408, 1412, 1416, 1407, 1405, 1403, 1401. We are going to be finishing 1413 and 1411 by the end of this week. The next five addresses to be worked on are as follows: 1409, 1420, 1424, 1428, 1432. (These should […]

  • Countrywood Park Update

    1459 Building: Completely finished with gate. 1400: old fence removed, new vinyl installed, needs gate. 1404: old fence removed, new vinyl installed, needs gate. 1408: old fence removed, new vinyl almost done being installed, needs gate. 1412: old fence removed, new vinyl almost done being installed, needs gate. 1416: removal of old fence will be […]

  • Countrywood Park II- fence project notice

    We are currently posting an information notice for the homeowners throughout the community. The fence notice states: Waddell Painting and General Contracting has been contracted to remove all of the wood fencing throughout your association and replace it with new vinyl fencing. This project will be completed over the next three month period. The closer […]

  • Upland Hills Esates- gate colors

    You will be receiving a new notice re: front gate colors. The board has added 3 additional colors to chose from. So you have the following (5) options to have your front gate painted:  the standard color scheme color, scarlet past, teal fury, swiss coffee, almond or black.

  • Upland Hills Estates- color scheme #9

    Attention homeowner who received the color scheme #9 notice, your color scheme has now changed. You will receive color scheme #1 per the discussion of the board. You will be receiving a new notice with the new colors. Please contact our office at 909-980-4059 to let us know your front door color choice and your […]

  • Countrywood Park II

    Installation of the new vinyl fencing samples has begun at the unit 194 building. General project notices will be posted for each homeowner within the next day or so. They will contain a site map with the direction in which we will be working. A copy of that site map will also be posted on […]

  • Countrywood Park II

    The removal of the old wooden fencing started today at the unit 194 building.

  • Countrywood Park

    On Tuesday March 11, 2014 we will start the installation of sample Vinyl fencing at the unit 194 building.

  • Upland Hills Estates- Patio Covers/Security Screen Doors

    Please call in to our office if you would like an estimate to paint your patio cover (patio covers are not included in the associations painting project). This estimate/cost will be provided to you upon request. If you would like to have your Security Screen Door painted it will be $65.00 charged directly to the […]

  • Upland Hills Estates high pressure cleaning

    We will be starting the high pressure cleaning on Monday March 10th. Please make sure to close your windows and have your breakables put away or pushed towards the back of your patio area. (Refer to the start notice that is getting posted today).

  • Quail Creek- Front Doors

    On this Saturday March 8th we will be painting front doors throughout the association. (If the center of your front door has been painted then we will be painting the remaining edge that can only be seen while the door is open). We will be working on site from 7am to 3:30 pm. Your door […]

  • Upland Hills Estates- Front Door Colors

    We have posted notices throughout this years phase of the painting project. You have three colors to chose from for your front door/front entry gate. Please call our office to provide your selection. 909-980-4059. If you do not call in, you will receive the standard color for your scheme.  

  • Vantage Red Curbs

    Starting on Thursday February 6th we will be painting the red curbs, yellow curbs and white parking stripes throughout the association. We will have the areas conned off, please do not park where we are working. We will be posting notices on Monday.

  • Rain delay

    Due to the wet weather we are not working on site today. We will be back on Monday as long as it dries up.

  • Bon View

    We will be painting the following units starting on Monday February 3, 2014. 2038, 2028, 2026

  • Quail Creek update

    As of today all of the stucco and siding have been sprayed. There are about 6 buildings left to have the eaves sprayed. Then we just have trim left to do. The project is moving along nicely. If you have any questions please feel free to contact our on site foreman Carlos- wearing the red […]

  • Glendora Greens working direction

    We will be working from Amelia Ave through East Curtis Court and Around to Greenview Dr. There is a map posted on a previous blog post with the working direction marked on it. Also, if you have any questions please feel free to ask our foreman on site- who is wearing a red shirt. (All of […]

  • Glendora Greens

    The high pressure cleaning will be starting on Monday January 27th. Once the high pressure cleaning is done throughout the association we will be starting the prep work and then painting all of the wood throughout. Notices are going to be posted this afternoon with information. We are looking forward to working with your association.

  • Carefree Azusa- fence update

    Starting on Tuesday January 21, 2014 we will be working on the following fences: Removal and replacement of the front of the unit fencing at 371 Indian Dunes. Removal and replacement of the back fence at unit 325 Pebble Beach. Fixing the front part of the gate and Remove/Replacing the far back fence at 333 […]

  • Quail Creek

    We are back on site today. We started prepping the units in Buildings #3, 4, 5.  Tomorrow we will be prepping units 74, 73, 75, 76 and 81, 82, 83, 84. We will be starting to paint the stucco on the prepped units Wednesday.

  • College Green- La Verne completion

    It has been a pleasure working with your association. We are doing the final project completion walk today.

  • Mountain Gate

    It has been a pleasure working with your association. We are scheduled to do our final walk this coming Friday December 6th. Please make sure to let us know if you have any touch up concerns prior to the walk.

  • Upland Hills Estates- fence update

    Today we are working on installing the new fence at 1512/1468 Augusta. Tomorrow we are scheduled to remove the fence at 1486/1490 Augusta. *weather permitting.

  • Quail Creek- update

    The high pressure cleaning started today. Today we have completed buildings: 3, 4, 2, 6, 5. Tuesday we are going to do buildings: 19, 18, 17, 14, 13 Wednesday we will be finishing the remaining buildings. **Weather permitting. Then we will be working on garages and the pool area until after the holidays. We are requesting […]

  • Mountain Gate- update

    We are finishing up the final touch ups today and will be done with the project by the end of the day. It has been a pleasure working with your association.

  • Mountain Gate- front door/completion notice

    We are posting notices today for the painting of front doors this coming Saturday November 30th. ** Weather Permitting** On: Saturday November 30, 2013 We will be painting your front door, between 7am- 3pm. Please make arrangements to be home as your door will need to remain open for at least two hours to allow […]

  • Mountain Gate- update

    Today we are working on spraying the stucco on building number 11. We should be finishing up with the painting project within the week. *weather permitting. Please note: all of the wood replacement has been completed.

  • Casa Blanca- update

    Due to the wet weather we were not working on site yesterday and we are not working on site today. We will be back once the weather dries up.

  • Mountain Gate update

    We were not on site yesterday due to the rain. We are back onsite today and are hoping to finish up the wood replacement on the last building number 11.

  • Upland Hills Estates-fence project

    Due to the wet weather we were not onsite yesterday and will not be there today. If everything dries up we will be back tomorrow to paint the fence at 1182/1188 Winged Foot and to start the fence removal at 1512/1518 Augusta.

  • Amador- pressure washing update

    As of right now we are finished with the high pressure cleaning throughout the association.

  • College Green La Verne- update

    All of the stucco on the units throughout the association has now been painted. We are currently working on finishing up painting the trim.

  • Upland Hills Estates- 1512/1518 Augusta start date

    We will be starting the fence project at 1512/1518 Augusta on Thursday November 21st, weather permitting.

  • Amador-power washing

    High pressure cleaning of the units exteriors has started today. We are working in unit number order from 1 to 99. This project should take 2-3 days weather permitting.

  • Weather Delay- Saturday Nov 16

    Due to the wet weather we did not work on site Saturday November 16th. We are back on site today (Monday Nov 18th)

  • Mountain Gate update

    As of today everything up to building number 9 has been completed. We will be starting to prep and paint building number 9 tomorrow, weather permitting. We should be finished with the remaining 3 buildings within about one week or so.

  • Mountain Gate update

    Today we are working on building number seven. Tomorrow we are working on painting the stucco on building number 8.

  • Upland Hills Estates- 1182/1188 Winged Foot start date

    We will be starting the fence project at 1182/1188 Winged Foot on Monday November 18th.

  • Upland Hills Estates- fence project update

    We will be removing the old damaged wood fencing and replacing it with Hardi Cement board fencing for the following addresses: 1182/1188 Winged Foot 1512/1518 Augusta 1486/1490 Augusta 1476/1480 Augusta 1468/1476 Augusta 1436/1440 Augusta 1205/1209 UHDS Estimated 7-10 day time frame per fencing depending upon size.

  • Mountain Gate update

    As of today building number five is complete. Today we are working on spraying building number six. We are thinking that building number six will be done on Saturday. We are also going to be power washing buildings number 10 and 11 on Friday.

  • Mountain Gate- wood replacement update

    Today we are starting the damaged wood removal and replacement on the last three buildings. We have building number 9 (1133/1157/1159) building number 10 (1171/1173/1175) and building number 11 (1185/1189/1193) left to complete.

  • College Green update

    Today we are finishing up painting the stucco in color scheme #7- we have two more houses in this color scheme that need the stucco painted.. We will be starting to paint the stucco in color scheme #2  tomorrow.

  • Mountain Gate update

    As of today buildings 1, 2,3 and 4 are done. (Front doors have been done as well). Tomorrow we will start to spray the stucco on building number 5. Building number five is 1147, 1143, 1139, 1137.

  • Casa Blanca -start date-

    We will be starting the power washing on Tuesday November 12th so that Monday November 11th Veterans Holiday can be observed. Project start notices will be posted on Monday November 4th.

  • Mountain Gate update

    We are back working on site today. Building number three has been painted and we are working on painting the stucco on building number four. We are also working on wood removal and replacement on building number six.

  • Rain Delay

    Due to the rain we are not working on site today. We will return once it clears up.

  • Mt Gate paint update

    As of today here is where we are at… Buildings #1 and #2 have had their stucco and trim painted. We are painting the stucco and trim on building #4 (1155) and we will be prepping building #3 tomorrow.

  • Mountain Gate- painting update

    As of today this is where we are at with the painting: Building #1: the stucco has been painted and we are working on painting the trim. Building #2: we are working on painting the stucco. (Please see previous post of map with building numbers, we are working in number order from 1 to 11)

  • Mountain Gate- pressure cleaning update

    As of today we have high pressure cleaned all of the buildings except for the last two (Building #’s 10, 11).

  • Mountain Gate- pressure washing update

    Notices are being put up today for Buildings 5-11. We will be starting to high pressure clean these buildings on Friday October 18, 2013. Wood removal and replacement will follow the high pressure cleaning. * We are working in building number order.

  • Mountain Gate- update on pressure washing and wood replacement

    The high pressure cleaning of buildings 1, 2, 3 and 4 has been completed. The removal and replacement of damaged wood has been completed on buildings 1, 2 and 3. Wood replacement on building number 4 will be completed tomorrow.

  • Mountain Gate- color scheme selected

    The current painting project colors will be as follows: Dunn Edwards Paint Stucco- DE 6130 Wooded Acre (Acrihues Flat) Trim- DE 6128 Sand Dune (Spartashield Eggshell) Garage Doors- DEW Swiss Coffee Wrought Iron- DEA 158 Northern Territory

  • UHCCCA- project completion

    We are now finished with this years painting project. We have posted completion notices for the homeowners asking to let us know of any touch ups or concerns by September 30th. It has been a pleasure working with your association.

  • Mountain Gate- update

    The high pressure cleaning is starting today. We will also be marking wood for replacement. The damaged wood will be marked with green or red. (Green is for wood that has already been approved, red is for wood that needs approval for replacement from the association).

  • Mariposa Lane- wrought iron painting update

    The wrought iron painting project was completed this last Saturday September 21st. It has been a pleasure working with your association.

  • Upland Hills Country Club- project completion

    The current painting project is very close to completion. We have two front doors left to paint and touch ups. We will be posting a completion notice to homeowners within the next day or so.

  • UHCCCA- update

    Today we are working on painting back wrought iron fences and patio covers for the homeowners who have contracted with us to do so.

  • College Green- wood replacement

    All of the damaged wood removal and replacement has been completed. (Please note: after pressure cleaning more damaged wood may be found).  

  • College Green- Pressure Cleaning start date

    Monday September 23, 2013 we will be starting the high pressure cleaning of the homes on the North Side of the main street of the complex.

  • Mountain Gate- start date

    Starting on: September 23, 2013   Waddell Painting will begin high pressure washing the exteriors of the units throughout your complex. This high pressure wash is necessary before painting can get started on your unit. Please note: windows may be spotted after. Please make sure all windows are closed; valuables and breakables should be placed […]

  • Mariposa Lane- update

    As of today the pool wrought iron is done, the entry monument sign & columns are done and the front entrance wrought iron is done. Today we are working on the back homeowner wrought iron.

  • UHCCCA- front doors

    Tomorrow, Saturday 9/14, we will be painting front doors along Upland Hills Dr. North.

  • Carefree Azusa Fences

    Starting next Wednesday September 18th we will be removing and replacing wooden fences in the complex. Project address to be posted…..

  • UHCCCA- front doors

    We will be posting notices today for the painting of Front doors on this coming Saturday September 14th. Please contact our office before Friday if you need to schedule a specific time.

  • Vantage Front Doors

    We are have been forming a list of homeowners who would like for us to do their front doors. We will be lightly sanding, touching up the stain and applying one coat of clear finish. The cost is $125.00 billed directly to the homeowner and due upon completion. Right now the doors are on hold […]

  • Mariposa Lane

    Starting on Monday September 9th- we began to paint all of the wrought iron throughout the association. Please make sure to trim your plants back 6 inches from the wrought iron and to remove any mesh or personal items attached to the wrought iron.

  • College Green La Verne

    We are currently working throughout the association on damaged wood removal and replacement. Once the wood repairs have been made we will be posting notices for the high pressure cleaning and prep work to begin for the painting project.

  • UHCCCA- update

    We have finished over on the Sawgrass/Candlewood street side of the current painting project. We are now working on the Upland Hills Dr. North.

  • Blog updates

    Our blog website was down. We would like to apologize for the inconvenience  this may have caused.

  • UHCCCO- update

    Yesterday we worked on trimming the fascia for the last building on the Candlewood/Sawgrass project area. Last Saturday we painted front doors in this area as well. We have completed the high pressure cleaning for the Upland Hills Dr. North area of the project. Today we will start removing the damaged wood along Upland Hills […]

  • Bon View- update

    We started the high pressure cleaning of 2030, 2032 & 2034 Buildings.

  • College Green La Verne

    (Notices will be posted next week). We will be starting to remove and replace the damaged wood for the homeowners who have contracted with us to do so starting on Tuesday September 3rd.

  • Cedar Creek San Dimas- job completion

    Our final walk through on Friday August 16th went great. Saturday we finished up a few minor touch ups and are now completely finished with the painting project. It has been a pleasure working with your community.

  • Marywood- completion

    We will be finishing the current touch up project throughout the community today. It has been a pleasure working with you.

  • UHCCCO- front doors

    This Saturday will be our first attempt at painting the front doors throughout the Sawgrass/Candlewood units in this years painting project. We will be posting notices for homeowners tomorrow. Our crew will be there this coming Saturday August 24th from 7am to 3:30pm. Your door will need to be left open after painting for at […]

  • UHCCCA- Upland Hills Dr. North update

    On Thursday August 22 we are going to be starting the high pressure cleaning of the units along Upland Hills Dr. North. The high pressure cleaning will take 2-3 days. After the high pressure cleaning we will start working on the wood replacement (week of August 26-30th- pending board approval of wood). The painting will […]

  • Marywood- update

    Today we will be finishing up the stucco patch, caulking and prep work. Tomorrow we will start painting.

  • Upland Hills Estates- wrought iron painting project update

    We have completed the sanding for the wrought iron painting project. We are working on the welding. Most of the units have been primed. We are currently working on priming and applying the finish coat.

  • UHCCCA- update

    Sawgrass & Candlewood Update:   Today we are finishing up painting the stucco and pop-outs on the last building in color scheme #3. Color schemes #1 & 2 for Sawgrass and Candlewood have had the stucco and popout painting completed. We will be painting the trim after all of the stucco has been painted.

  • Marywood update

    The high pressure cleaning will be completed in about one hour. The painting touch ups will begin after lunch time.

  • Marywood- pressure cleaning notice

    The following notice will be posted 8/6/13: Notice to Homeowner **WEATHER PERMITTING** Starting on: Monday August 12, 2013   Waddell Painting will begin a light pressure washing of the exteriors of the units throughout your complex. This pressure wash is necessary before touch up painting can get started on your unit. Please note: windows may […]

  • Cedar Creek San Dimas- front door update

    Saturday we were able to paint all but 14 front doors throughout the association. Today we are working on touch up painting throughout the association. We will be starting to painting patio covers and decks for the homeowners who have contracted directly with us to do so.

  • UHCCCA- wood replacement update

    As of today  all of the high pressure cleaning along Sawgrass and Candlewood has been completed. We have started the prep work as well. Today we have started removing the damaged wood and will be replacing it with new. We will be working on the wood replacement most of the week. Painting should be starting […]

  • Cedar Creek San Dimas- update

      Notice to Homeowners ** Weather Permitting** On: Saturday August 3, 2013 We will be painting you’re the remaining edge around your front door, between 7am- 3pm. Please make arrangements to be home as your door will need to remain open for at least two hours to allow for proper drying ———————————————————————————————————————-   Also, please […]

  • UHCCCA- color information

    Vista Paint Colors:   Color Scheme #1: (1649/1653/1655 Candlewood, 1299/1305/1309 UHDN, 1355/1361/1365 UHDN, 1250/1254/1262, pool house #5) Body/garage doors- 72 Toga Garage Inset- 43 Sandpebble Trim-59 Bone White (eggshell)   Color Scheme #2: (1617/1621/1625 Candlewood, 1275/1283/1287/1293 UHDN) Body/garage doors-8457 Bamboo Beach Garage Inset- 97 Mesquite Trim- 59 Bone White   Color Scheme #3 (1583/1587/1591 Sawgrass, […]

  • UHCCCA- high pressure cleaning update

    We started the high pressure cleaning today down at the 1583 Sawgrass Building. We have done the 1583/1587/1591 Sawgrass and 1595/1599/1603, 1609/1613 Sawgrass. We are currently pressure cleaning the 1617 Candlewood. Tomorrow 7/30/13 we will be starting at 1621 Candlewood.

  • UHCCCA- project start date

    It’s that time of year again! We will be posting start notices for the current paint project phase on Monday July 22nd to start the high pressure cleaning on Monday July 29th.

  • Upland Hills Estates- update

    We are working on finishing up the current painting phase. Saturday we will have a crew throughout the association working on touch ups and painting patio covers for the homeowners who have contracted us to do so. Please feel free to point out any concerns that you may have, or call in to our office […]

  • Cedar Creek San Dimas

    Today we are currently working at 550 Pistol Creek Loop. The first five buildings are done: (102/106/110/114, 118/122/126/130, 134/138/142, 115/119/123 Via Vacquero and 551/555/559 Pistol Creek Loop) We will be moving to the 143/147/151/155 Via Vacquero Building Next.

  • Bon View- 2036 Bldg

    The high pressure cleaning of the 2036 building has been completed. We are currently prepping the building for paint.

  • Cedar Creek San Dimas- update

    The pool area wood repair/replacement is going to be completed today. The first three buildings are done: 102/106/110/114, 118/122/126/130 and 134/138/142 Via Vaquero. We are working on 115/119/123 Via Vaquero and then will be moving to 55/555/509 Pistol Creek.

  • Bon View- project start date

    Notices were posted on Monday July 8th letting the homeowners of the 2036 Building know that we will be starting their portion of the project on Monday July 15th. High pressure cleaning of the complete exterior will be the first item started on that Monday. Prep work will then follow.

  • Upland Hills Estates- close to completion

    The current painting project is very close to completion. We have posted a notice to let all of the homeowners know. The notice asks that if you have any comments or concerns to please bring them to our attention by Friday July 19th. You can call our office at 909-980-4059 or email Natalie at Natalie@waddellpainting.net to […]

  • Wyeth Cove Fence Staining Project

    We will be at your community on this Saturday July 13th to complete the fence staining project for the homeowners who have contracted with us. The approved stain color is: Port Wine.

  • Cedar Creek San Dimas- update

    We hope that you had a safe and happy 4th of July. Today we are working on painting the finish coat on the second building. (118/122 Via Vaquero and then will start the 123/130 units) The next building to receive the finish coat will be 134/138/142 Via Vaquero.   We are done with the first […]

  • Upland Hills Estates- cypress update

    We hope you had a happy and safe 4th of July. Today we are spraying the last building on Cypress- color scheme #10 1591 Cypress. We are also working on replacing the wood that was previously removed on Cypress. Later today we will be working on painting the pop-outs along Cypress.

  • Cedar Creek San Dimas- update

    Today we are starting to apply the finish coat of paint to building number one: 102/106/110/114 Via Vaquero. We will be working in the same direction that we did with the prep/wood repair.

  • Cedar Creek San Dimas- deck/patio cover reminder

    Just a reminder that if you have received and estimate to paint or stain your deck or patio cover- please let us know as soon as possible if you would like to have the work completed. We will need to complete these additional items while we are still working on the current painting project throughout […]

  • Upland Hills Estates update

    As of today Upland Hills Dr South has been finished. We are working on Cypress: the stucco and popouts- 1599 color scheme #2- stucco and popouts are done 1597 color scheme #3- stucco and popouts are done 1591 color scheme #10- not done yet 1589 color scheme #8- not done yet 1583 color scheme #5- […]

  • Cedar Creek Villas San Dimas update

    As of today all of the wood removal and replacement has been completed. Today we are working on prepping the last building: scrape/sand and caulking. 116/112/108/104 Cedar Creek Rd. Tomorrow we will be priming the last building: 116/112/1108/104 Cedar Creek Rd. Monday we will be starting to paint the finish coat on the first building: […]

  • July 4th Holiday

    We will be closed on July 4th, 5th and 6th in observance of the 4th of July Holiday. Our crews will not be working on site so that homeowners will not be inconvenienced while trying to celebrate in the nice weather outside. We will resume the project on Monday July 8th. We hope you have a happy […]

  • Upland Hills Estates- Update

    Saturday we worked on touch up and painting the wood trim along Upland Hills Dr. South.   Today we have started removing the damaged wood along Cypress. We are also working on priming the new wood and installing it back up where it has been removed along Upland Hills Dr. South.

  • Upland Hills Estates- wood replacement and trim painting update

    Here is an update as of today: Wood: Removal and replacement of damaged wood has been completed on the first two buildings on the North side heading East and we are working on the third building 1181/1185. Trim: Painting of the “white” swiss-coffee trim color has been completed on the first four buildings on the […]

  • Cedar Creek San Dimas- update

    As of today all of the wood replacement, prep work and priming has been completed along Via Vaquero. We are now turning the corner onto Cedar Creek Road (164/160/158/152 is the first building on this street).

  • Cedar Creek San Dimas- update

    Today we are working at 171 Via Vaquero. We will be moving next to the 164/160/158/152 Cedar Creek Road building.

  • Upland Hills Estates-Fascia/Trim update

    Today we are working on painting the fascia/trim on the units. We are working West to East along the North Side of the street Upland Hills Dr. South. As of right now the following units have been completed: 1167/1169, 1175/1177 and we are working at 1181/1185.

  • Front Door update

    On Saturday we were able to complete the painting of the front doors on most of the units on Upland Hills Dr. South. If you were not able to be home please contact our office to schedule an appointment or contact our foreman onsite (Carlos in the red shirt).

  • Cedar Creek San Dimas update

    Today we are working at 159 and 163 Via Vaquero (the last building on this street). The next building will be 164/160/158/152 Cedar Creek Road.

  • Cedar Creek San Dimas- update

    Today we are working on 147/151 Via Vaquero. We will be at 155 and then moving to the 159/168/167/171 Building.

  • Upland Hills Estates- update

    Yesterday and today we have been working on color scheme #10: 1181/1185 and 1204/1208 Upland Hills Dr. South.

  • Upland Hills Estates- update

    Today we are working on color scheme #9: 1219/1223 and 1168/1170. Tomorrow we will be working on the trim and electrical/water heater doors on color schemes #6 & 7.

  • Cedar Creek San Dimas- update

    As of today we have primed and completed the wood replacement on the first three buildings: 102-114, 118-130, 134-142 Via Vacquero. We are working on removing and replacing the damaged wood on 115/119/123 building.

  • Upland Hills Estates- update

    As of today we have the following units left that need to have the stucco painted: 1168/1170-scheme #9 UHDS, 1181/1185 & 1204/1208- scheme #10 UHDS. This totals 3 buildings left on Upland Hills Dr. South and then the four buildings on Cypress.

  • Cedar Creek San Dimas- update

    Today we are working on priming the siding. We are at 126 and 130 Via Vaquero and will be moving to 134 next.

  • Upland Hills Estates- update

    Today we are working on removing damaged wood. We started on the North West Side of Upland Hills Dr. South. We have already removed the wood on the following units: 1167/1169, 1175/1177, 1181/1185 and we are working at 1189/1193.

  • Cedar Creek San Dimas- update

    Today we are working on priming the first building: 102/106/110/114. We are also working on removing and replacing the damaged wood at 134/138/142 Building.

  • Upland Hills Estates- Update

    Saturday we were able to paint all of the electrical and water heater doors for colors schemes #2, 3 & 4 on Upland Hills Dr. South.   Today we are painting the stucco on color scheme #4: starting at 1205/1209 and then moving to 1182/1184 Upland Hills Dr. South.

  • Cedar Creek San Dimas colors

    Here are the paint colors: (Vista Paint)   California Rustic (lighter brown) Oxford Brown (darker brown eggshell finish for the garage doors in California Rustic

  • Upland Hills Estates- update

    Today we are working on painting color scheme #3. We have started the 1175/1177 units on the North West Side of Upland Hills Dr. South. We will then be moving to 1212/1216 on the South East Side of Upland Hills Dr. South.

  • Cedar Creek San Dimas update

    Today we are continuing with the prep work on the 115/119/123 Building.   We will also be starting to remove and replace damaged wood. (Once the wood delivery is made this morning). Wood replacement will start at the 102/106/110/114 Building.

  • Cedar Creek San Dimas- update

    Today we are prepping the 115/119/123 Via Vaquero Building. (These three buildings are done with the prep work: 102/106/110/114,   118/122/126/130,   134/138/142)   We will be moving to the 559/555/551 Building next.

  • Upland Hills Estates- Update

    Today we are working on prepping the remaining units on the SouthWest side of UHDS. We have the following units left to prep: 1192/1188, 1184/1182, 1178/1174, 1170/1168.   We are also working on painting the window trim and pop-outs in color scheme #2: 1167/1169 and 1218/1222 UHDS.

  • Cedar Creek Village San Dimas- update

    We have prepped the following units: 102/106/110/114, 118/122/126/130 and are working on prepping 134/138/142.

  • Upland Hills Estates- Update

    Prep-work update: All of the North Side of Upland Hills Dr. South has been prepped (1167/1169/1175/1177/1181/1185/1189/1193/1197/1201/1205/1209/1211/1215/1219/1223). On the South Side of Upland Hills Dr. South we have prepped 1222/1218/1216/1212/1208 and are currently prepping 1204.   Prime Work: We have primed the eaves on the following units along the North side of Upland Hills Dr. South: […]

  • Closed Monday 5/27/13

    We will be closed on Monday May 27th in honor of Memorial Day. Our crews will not be working on site. All projects will resume on Tuesday. Have a great Holiday!

  • Cedar Creek San Dimas- update

    The high pressure cleaning and been completed. Today we worked on prepping the first building (102/106/110/114) to make it ready for paint. Wood removal and replacement will start next week after board approval of wood repairs.

  • Upland Hills Estates- update

    As of today the high pressure cleaning has been completed. Today we are working on marking damaged wood in need of replacement. Once we have the wood marked we will be making a list for replacement for board approval.

  • Cedar Creek San Dimas- update

    Today we are continuing with the high pressure cleaning of the unit exteriors. We are also marking damage wood for replacement. We will be submitting a wood repair bid to the association for approval.

  • Beaumont Terrace Co Op- Update

    Today we are finishing up painting the metal and that will complete the project. It has been a pleasure working with you.

  • Cedar Creek San Dimas- pressure cleaning update

    Today we are starting the high pressure cleaning to be done throughout the association. We are starting at the 102/106/110/114 Building (The first building on the right hand side when you enter the complex). We are also marking the damaged wood and will be submitting a proposal to the association for wood replacement.

  • Carefree Azusa- Annandale

    Today we are working on removing the fences at 321-350 and 351 Annandale. We will be setting new posts in cement and installing new wood fences. Once the new fences are up, we will be painting them.

  • Beaumont Terrace Co Op -update

    Today we are working on painting the metal and doing touch ups throughout.

  • Upland Hills Estates- Wood Repair and Prep Work

    Tomorrow we will be starting to mark damaged wood that needs to be replaced- pending association approval. We are also going to start the prep work. The prep work will be done in the same order as the high pressure cleaning. Starting on the North side of  Upland Hills Dr. South- going From West to East. […]

  • Upland Hills Estates- Pressure cleaning update

    Today we are high pressure cleaning the exteriors of the units on Cypress ( 1599-1577 Cypress). These units are the last ones that need to be pressure cleaned and then the prep work will start. See next post on prep work schedule

  • Beaumont Terrace Co-op update

    The painting project is getting close to completion. Today we worked on painting metal items, doors, gates, posts and stucco popouts.

  • Upland Hills Estates- Pressure cleaning update

    Today we started the high pressure cleaning at 1204 Upland Hills Dr. South. Right now we are currently finishing up 1170/1168 the last two units on the street. We will then be moving over to Cypress- starting at 1599 and working towards 1577 (North to South). We might only be able to finish pressure cleaning […]

  • Upland Hills Estates- pressure cleaning update

    Today we were able to high pressure clean units Upland Hills Dr. South: 1211, 1215, 1219, 1223, 1222, 1218, 1216, 1212 and 1208. We will be starting at unit #1204 tomorrow and working towards 1168 Upland Hills Dr. South. (South side of the street going West)

  • Beaumont Terrace Co Op- update

    All of the stucco has been painted. We are currently working on painting the eaves, trim and popouts.

  • Upland Hills Estates- pressure cleaning update

    Today we were able to complete the high pressure cleaning of the following units in order from West to East on the North Side of Upland Hills Dr. S.: 1167, 1169, 1175, 1177, 1181, 1185, 1189, 1193, 1197, 1201, 1205 and  1209. Tomorrow we will be starting at 1211 Upland Hills Dr. South. We will […]

  • Upland Hills Estates update

    We are starting the high pressure cleaning today. We are also going to be out there today measuring up patio covers for the homeowners who have requested bids to paint them.

  • Upland Hills Estates- pressure cleaning direction

    We are starting the high pressure cleaning tomorrow. We will be working on Upland Hills Dr. South. We will be starting on the North side of the Street working From West to East and then the South Side of the Street working from East to West.

  • Upland Hills Estates- Pressure Cleaning Start Date

    Notice to Homeowner **WEATHER PERMITTING** Starting on: Wednesday May 15, 2013 Waddell Painting will begin high pressure washing the exteriors of the units throughout this phase of the project. This high pressure wash is necessary before painting can get started on your unit. Please note: windows may be spotted after. Please make sure all windows […]

  • Beaumont Terrace Co Op

    High pressure cleaning of the exteriors started today. This high pressure wash is necessary before the painting of you unit can get started. Please note: windows may be spotted after. Please make sure all windows are closed; valuables and breakables should be placed out of the way, to insure there are not difficulties with the […]

  • Montclair Town Homes Phase 1 update

    The last remaining touch ups for Phase #1 are being completed today. We will be painting the door edges on this coming Saturday.

  • Montclair Town Homes- Phase one update

    As of today all of the stucco and siding in phase #1 has been painted. We are working on the eaves and trim.

  • Montclair Town Homes- update

    The high pressure cleaning of the units in phase #1 has been completed. Wood Repair: we will be starting to remove and replace the damaged wood tomorrow. 4/23 Prep work: today we are working on patching stucco & priming siding and eaves. We are prepping the following units: 10474, 10472, 10478, 10476, 1046410462, 10468, 10466, 4536, […]

  • Vantage- touch up kits

    Dunn Edwards Paint touch up kits are currently being assembled and will be delivered on site shortly. Thank you for your patience.

  • Upland Hills Estates- Front Door Color Selection

    Just a reminder to fax 909-987-6660 or mail in your front door color selection. Thank you to the homeowners who have done so already.

  • Upland Hills Estates- Baseline wrought iron painting

    We are finishing up painting the wrought iron fencing along Baseline today. Tomorrow we will be painting by the entrance.

  • Vantage- completion

    Please take a minute to note any touch ups needed around your unit as per the last notice posted. We will be back on Saturday April 27th to complete any  touch ups and to refinish front doors that have been requested as per homeowners. If you would like to have your front door refinished- lightly […]

  • Montclair Town Homes- Phase 1 pressure cleaning update

    We started the high pressure cleaning of the exteriors of the units in paint phase #1 on Tuesday. (A one day delay due to the rain). Today we are finishing up the last two buildings in this phase. Wood removal and replacement will immediately follow along with the prep work to make the buildings ready for […]

  • Upland Hills Estates- 2013 Color Schemes

    Following are the color schemes that will be used for this years painting project…. (In addition to the stardard front door color, the homeowners will have the option to choose either DEA 150 Scarlet Past or DE 5762 Teal Fury). Scheme #2: (1167/1169, 1218/1222 UHDS & 1599 Cypress) Body: DEC 726 Adobe Fascia: DEW 341 Swiss […]

  • ^^Upland Hills Estates 2013 Painting Project^^^

    ^^^^^^^^^^^^^^^^^^2013 Painting Project^^^^^^^^^^^^^^^^^^

  • Montclair Town Homes- start notice

    We will be posting a start notice for the homeowners who are in the phase for the upcoming painting project. More information to follow shortly.

  • Vantage- close to completion

    The Vantage exterior painting project is close to completion. Today we are working on the entrace gate and homeowner front doors. Please remember to call in if you would like to have your front door refinished- lightly sanded, touch up the stain and one coat of clear finish. The cost is $125.00 while we are […]

  • Vantage update

    Today we are working on painting the lights. After the lights are completed all that we will have left to do is to paint the pool patio covers. The project is very close to completion.

  • Vantage- Front Door Reminder

    Just a reminder that if you would like to have your front door refinished: lightly sanded, touch up the stain and one coat of clear finish- please contact our office asap to schedule. The cost of $125.00 is billed directly to you, not the association. *This price is only valid while we are working in […]

  • Vantage update

    Yesterday we finished painting the trim in color schemes 1 and 2. Today we are working on painting the trim in color schemes 3 and 5. We are also working on stucco touch ups. We have the black lights left to paint and will be doing all of them on the same day- date to […]

  • Vantage update

    Today we are working on painting the trim in color schemes 1 and 2.

  • Vantage Update

    As of today the following units have had their stucco painted: Scheme #1: 866, 832, pool house Scheme#2: 880, 870, 868, 836, 822, 808 Scheme #3: 856, 806 Scheme #5: 860, 838, 816, *We are finishing up 810 that is the last unit in color scheme #5. We are starting color scheme #6: 872, 862, […]

  • Vantage update

    We are back working on site today. We are finishing up the stucco in color scheme number one and starting the stucco in color scheme number two. Please see yesterdays post for color scheme addresses.

  • Vantage updates

    If the weather cooperates we will be back tomorrow to finish up the stucco in color scheme #1: the pool house and 866 & 832. Then we should be starting painting the stucco in color scheme #2: 868, 870,  880, 836, 822 &808.

  • Vantage Update- weather delay

    We are not working on site today due to the wet weather. We will be back hopefully tomorrow when it dries up.

  • Vantage- color scheme #1

    Today we are working painting the stucco for color scheme #1: on the pool house and units: 866 &832.

  • Vantage- update

    We have been working really hard this week on prepping the remaining units for paint.( The Southeast Side of the Complex) We are almost done with the prep work (caulking, stucco patches, re-nailing loose wood, sanding/scraping etc).

  • Vantage- update

    We are back working on site today. We are working on the remaining homes on the south east side of complex.

  • Vantage-update

    We are not working on site today in observance of the Chinese New Year- per the homeowners request. We will be back Wednesday to start the homes on the South East Side.

  • Vantage-Saturday door update

    Today we are working on painting french doors and the garage man doors.

  • Vantage update

    Today we are completing a few things as follows: We have some of the guys painting the center of the doors- getting them ready for Saturday. On Saturday we will be painting the remaining edges that are exposed when the doors are opened. **Weather permitting. We have some of the guys painting mail boxes and […]

  • Vantage- project update

    All of the stucco has now been painted. The eaves have been painted in color scheme #1. The eaves in color scheme #2 are almost done and we are also working on the eaves in color scheme #5. The garage roll up doors are almost all painted- we have color scheme #7 and #6 left […]

  • Vantage- Stucco Painting Update

    Here is a stucco painting update: Color Scheme #1- we are starting to paint the stucco today. We are starting at unit 916. Color Scheme #2- all of the stucco has been painted Color Scheme #3- the stucco paintng is on hold pending color decision Color Scheme #4- not started yet Color Scheme #5- all […]

  • Vantage rain delay

    Due to the rainy weather today, we are not working on site.  We will be back as soon at it clears up.

  • Vantage- stucco painting update

    All of the stucco in color scheme #2 has been completed. We have put color scheme #3 on hold- as the board may change the stucco color. (Color scheme #1 is also on hold- the board may change that stucco color as well). There aren’t any units with color scheme #4 on the south side. […]

  • Vantage Front Door Update

    If you have called in to our office to approve to have your front door refinished- we have started prepping the approved list’s doors. We will be prepping during this week and then applying the clear coat on Saturday. The prep work includes sanding, filling of cracks and touching up the stain. We have scheduled […]

  • Vantage Painting Project Update

    The plan for the painting project on the south side of the complex is to paint all of the stucco on the units first, and then come back to paint the trim. We put a sample up for the stucco color in scheme number one and are waiting for an approval- because the stucco color […]

  • Vantage Front Door Notice

      Front Doors Please call in to our office at 909-980-4059 if you would like to be put on our list to have your front door refinished. We will be light sanding, touching up the stain and then applying one coat of poly urethane finish. The price for you to have your front door refinished […]

  • Vantage- rain delay

    We are not working on site today due to the wet weather. We will return as soon as it dries up.

  • Vantage- pressure cleaning update

    Our crew was able to complete the high pressure cleaning today. We will be back tomorrow to start the preparation for painting.

  • Vantage-pressure cleaning update

    Today we started the high pressure cleaning of the south side of the complex. We started on the West side and are working East. As of right now we have high pressure cleaned the following units: 930, 928, 926, 922, 920, 918, 936, 912, 910, 908, 892. Carlos, our foreman in the red shirt, is […]

  • Vantage- project schedule

    We will be back to the Vantage Association to resume the painting project after the Holidays. Our scheduled return date is  Monday January 7th. We will be starting back up with the high pressure cleaning of the units along the south side of the complex. Homeowners will be receiving notices prior to the start.

  • Amador- wrought iron

    We are working on painting the wrought iron throughout the assocation again today.

  • Vantage door painting

    This past Saturday December 8th was our second attempt at painting the french doors throughout the North side of the complex. We were able to paint a lot of them. For the few that were not home/unable to be painted, we will be planning another door painting day. We will post a notice to those […]

  • Amador update

    Today we have a crew working on the painting of light posts and wrought iron gates throughout the association.

  • Vantage- French Doors

    We will be trying to paint any remaining French doors this coming Saturday December 8th. Please contact our office if you would like to schedule a specific time.

  • Vantage touch ups

    Today we are working on touch ups along the Northside of the complex. We are also going to be painting French doors for units that were not painted last Saturday. (if the homeowners are there and willing to have them done).

  • Amador- touch ups

    We have a crew working throughout the association today to complete any touch ups that we might have previously missed.

  • Central Workshops

    We have a few touch ups remaining at the business park and the signs. We will be working on painting the signs in the evening time during this week. After the signs are completed we will be scheduling a final walk with the board.

  • Vantage- stucco patching/french door updates

    We were not working on site yesterday due to the rainy wet weather. But we are back today. We are working on the 803 Building doing stucco patching.   Saturday Decemeber 1st we were able to paint a majority of the french doors but there are still some left. We will be planning another Saturday […]

  • Vantage- rain delay

    Due to the wet weather, we are not working on site today. We will be back when it dries up.

  • Vantage- French Door painting notice

    Today we are hanging the notices to paint the French Doors. Weather permitting we will be painting the French Doors this coming Saturday December 1st. The doors will need to remain open for 2-3 hours to allow for proper drying. If you need to schedule a specific time for us to paint your French doors […]

  • Vantage update

    Today we are finishing up the touch ups on the last building ( #933). We are also working on stucco patching on the first building ( #801).

  • Central Workshops update

    On Friday(11/23/12) we were able to complete everything except for the painting of the signs. The signs will be painted shortly and that will conclude the painting project.

  • Vantage update

    Today we are working on touching up all of the buildings that have been completed along the North side of the complex.

  • Vantage- Thanks Giving Schedule

    We are working on site today but we will be off for the rest of the week. (This will allow time for the homeowners to celebrate the Holiday without being interupted by our crew). We hope you have a happy and safe Thanks Giving.

  • Vantage Light painting update

    Today we are working on finishing up the painting of the lights on the last (3) Buildings on the North side of the complex. (830, 923, 933)

  • Upland Hills Estates- fence project

    Today we are starting the fence removal and replacement project for the following addresses: 1178/1180 Winged Foot 1172/1176 Winged Foot  

  • Vantage Update

    On Saturday we had a crew over there on the North side of the complex painting lights. Today we are also working on painting the lights. We have done 801, 803, 817, 827, 851 and are working on 863 & 873. We have four more buildings left to paint the lights.

  • Central Workshops Update

    The only items left on the buildings are a few touch ups, the signs and the roof access ladders. Then we have miscellaneous items in the parking lot area, like light poles. Our goal is to be completely finished this coming weekend.

  • Central Workshops- update

    Today we are working on painting the lines on the building.

  • Vantage 933 update

    Building 933: today we are working on painting the eaves on this building.

  • Vantage 933 update

    Building 933- today we are working on spraying the stucco on this building.

  • Central Workshops update

    Today we are finishing up spraying the body. We are also painting the lines. Next weekend we will be working on the door frames.

  • Vantage Bldg 933 update

    Building 933- today we are working on spraying the stucco on this building.

  • Upland Hills Country Club Condo Assocation- 2012 Vista Paint Color Schemes

    Here are the Vista Paint Color Schemes for this Phase of the 2012 Painting Project: (Please note: if you would like to see a preview of what the actual color looks like, find your color scheme below- listed by your address number, and then visit http://www.vistapaint.com/color-chips/palette and enter the color name or color number). Color […]

  • Upland Hills Estates- 2012 color schemes

    Scheme #1: 1166 Winged Foot, 1168 Winged Foot, 1204 Winged Foot, 1206 Winged Foot, 1250 Winged Foot, 1252 Winged Foot Body- w704 Acriflat: DEC 770 Drifting Trim-W704 Acriflat: DEW341 Swiss Coffee Accent Trim/Pop-outs: W704 Ariflat: DEC 750 Bison Beige Doors/Shutters/Iron: W901 /42-53v DE6062 Tea Bag   Scheme #2: 1170 Winged Foot, 1172 Winged Foot, 1212 […]

  • Vantage- weather delay

    Due to the rainy weather we are not working on site today. We will be back hopefully tomorrow if it is dry enough.

  • Vantage Color Schemes

    Building #    Scheme: Terrace Lane East 802     7 806      3 808     2 810     5 812     6 816     5 818     7 820     6 822     2 826     7 828     7 830     8 832     1 836     2 838     5 850     9 852     6 856     3 860     5 862     6 866     1 868     2 870     2 872     6 876     […]

  • Vantage 922 & 933 Building

    Building #922- Today we are working on finishing up the stucco and we might start painting the eaves this afternoon. Building #933- Later today we will be starting the prep work on this building.

  • Vantage- south side of complex

    We will be posting notices within the next few days for the pressure cleaning to start on the south side of the complex. We will blog an update with a start date as soon as that is determined.

  • Vantage 922

    Building 922 update- Friday we worked on prepping this building. Today we have started spraying the stucco. We are also working on masking today.

  • Vantage 893 update

    Building 893- today we are working on spraying the stucco.

  • Vantage 883 & 893 update

    Building #893- today we are starting to spray the stucco. We are also still working on masking this building. Building #883- this building is now finished.

  • Vantage 883 & 893 updates

    Building 883- today we are working on touching up this building.   Building 893- today we are working on prepping this building.

  • Amador- pool house color scheme

    Pool House and Out Buildings   Body- DE 6141 Salt Box Trim- DE 6077 Deep Brown Popouts- DE 6077 Deep Brown Shutters/Doors- DE 6313 Enchanted Eave Gate Center- DE 6075 Wood Lake

  • Amador color schemes Bldgs 21-31

    Building #21: Body- DE 6157 Bisque Tan Trim- DE 6069 Bannister Brown Popouts- DE 6216 Barrel Stove Shutters/Doors- DE 5872 Lakeville Front Gates- DE 6124 Whole Wheat   Building #22 Body- DE 6152 Maple View Trim- DE 6069 Bannister Brown Popouts- DEW 341 Swiss Coffee Shutters/Doors- De 6320 Pike Lake Front Gates- DE 6124 Whole […]

  • Amador color schemes Bldgs 11-20

    Building #11: Body- DE 6141 Salt Box Trim- DE 6125 Carved Wood Popouts- DE 6125 Carved Wood Shutters/Doors- DE 6076 Wondering Road Front Gates- DE 6124 Whole Wheat   Building #12: Body- DEC 728 Madera Trim- DE 6216 Barrel Stove Popouts- DE 6216 Barrel Stove Shutters/Doors- DE 6076 Wondering Road Front Gates- DE 6124 Whole […]

  • Amador- color schemes bldgs 1-10

    Building #1: Body- DE 6152 Maple View Trim- DE 6069 Bannister Brown Popouts- DEW 341 Swiss Coffee Shutters/Doors- DE 6320 Pike Lake Front Gates- DE 6124 Whole Wheat   Building #2: Body- DE 728 Madera Trim- DE 6216 Barrel Stove Popouts- DE 6216 Barrel Stove Shutters/Doors- DE 6028 Dark Ruby Front Gate- DE 6124 Whole […]

  • Central Workshops Association

    This past weekend we completed the prep work so now the buildings are ready for paint.

  • Vantage 883 update

    Building 883- today we are working on spraying the eaves for this building.

  • Vantage 873 883 updates

    Building 873: this building is now done. Building 883: today we are working on spraying the stucco on this building.

  • Vantage 873 & 883 updates

    Building: 883- today we have started working on prepping this building for paint. Building: 873- today we are finishing up painting the trim and shutters on this building.

  • Vantage 873 Building

    Building 873: today we are working on finishing up spraying the stucco and are starting to spray the eaves.

  • Central Workshop Colors

    The new colors for Central Workshop are as follows: DE6143 Almond Latte for the building DE6145 Rocky Ridge for the columns DE6083 Badlands Sunset for the stripe, fascia boards, light poles and wrought iron. Dunn Edwards Paint.

  • Vantage- Bldg 873 update

    Building 873: today we are working on spraying the stucco on this building.

  • Vantage- 873 Building

    We are working on prepping this building today. Paint should be starting on Monday for this building.

  • Central Workshops Association

    We will be putting up more color samples on Monday for the board to look at. Once they make a color selection next week we will be back to resume the painting project on Saturday Oct 27th.

  • Vantage- 863 & 873 Updates

    Building 863: today we are working on painting the eaves, trim, shutters and garage doors. Building 873: we are going to start prepping this building later on this afternoon.

  • Vantage- 863 & 873 Update

    Building 863: today we are spraying the eaves on this building. Building 873: tomorrow we might start prepping this building.

  • Vantage- 863 Building update

    Building #863: today we are working on spraying the stucco and masking more on this building.

  • Amador

    Saturday’s touch up and front door painting went very well. There are 10 front doors that we were not able to have access to paint while open. We will be scheduling another door painting day to finish painting the edge for those doors. We will post that day as soon as possible.

  • Vantage- rain delay

    Due to the current rainy weather we are not working on site today. We will be back when it dries up.

  • Vantage- entry fences & 863 update

    Today we are working on spraying the entry fences. We are also masking the 863 Building.

  • Amador- front doors/completion notice

    We are finishing up today. We are also posting a notice today for the painting of the front doors this coming Saturday October 13th- weather permitting. Your door will need to remain open for atleast 2-3 hours to allow for proper drying. If you need to schedule a specific time to have your door painted […]

  • Amador update

    Today we are spraying the eaves in the pool area and painting the trim on the out building on the East side by the entrance. The west side out building is done. We should be finishing up all of the out buildings tomorrow. We will be posting a notice for front doors shortly.

  • Vantage- 851 & 863

    Building 851- today we are working on painting the trim. Building 863- today we are working on prepping this building.

  • Vantage- Building 851

    Building: 851- today we are spraying the stucco on the garage side of the building.

  • Amador- pool area and west out building

    Today we are working on painting the trim in the pool area and we are painting the out building on the west side of the complex.

  • Central Workshops

    This past Saturday October 6th and Sunday October 7th we were able to high pressure clean all of the buildings. We also worked on prepping the buildings for paint. The color samples are up above the garages at Unit #66. We will be painting next Saturday and Sunday.

  • Vantage- 827 & 851 updates

    Building # 827- today we are painting the trim on this building. Building # 851- today we have started prepping this building.

  • Amador- pool area and shutter update

    All of the shutters throughout the association are now completely painted. We are working in the pool area today.

  • Amador- pool area and shutters update

    Today we are working on painting in the pool area and the shutters. There are about 7 buildings left that need to have the shutters painted, we should be finishing them up tomorrow.

  • Vantage- 851 Bldg

    Building 851- we  will be starting the prep work for this building tomorrow (Thursday 10/4/12).

  • Vantage – 827 Bldg

    We are almost done painting the eaves. We are also working on painting the trim today.

  • Vantage- Bldg 827

    Today we finished spryaing the stucco and right now we are starting to work on the eaves.

  • Amador- update

    We are still working on painting the shutters today.

  • Vantage- 827 update

    Today we are spraying the stucco on building 827. We are also masking the windows and ground for this building.

  • Amador-shutters update

    Today we are working on painting the shutters throughout the complex.

  • Amador- building 33 and pool area update

    Today we are finishing up painting the trim on the last building #33. We are also working in the pool area, painting the cabanas.

  • Vantage- 817, 827 update

    Building 817- today we are working on touching up the shutters. Building 827- today we are working on prepping this building, to get it ready for paint on Monday.

  • Central Workshop Association- pressure cleaning notice

    Notices are going to be posted today…. The high pressure cleaning will be started on Saturday October 6th. This high pressure wash is necessary before painting can get started on your unit. Please note: windows may be spotted after. This painting project will be done on Saturdays and Sundays to minimize the inconvenience to the […]

  • Amador- 31, 32, 33 updates & pool area

    Bldg 31- we sprayed and painted the trim on this building yesterday. Bldg- 32- we sprayed the eaves on this building yesterday and today we are working on painting the trim. Bldg- 33 we are spraying the eaves on this building today. We are going to start working on the pool area cabanas tomorrow. We […]

  • Vantage- 801, 803, 817, 827 updates

    801- we worked on painting the shutters today. 803- we worked on painting the shutters today. 817- we worked on painting the shutters today and the trim. 827- we have a crew working on prepping this building today.

  • Amador- 28, 29, 30 update

    Building #28- is all done except for the shutters. Building #29- we are working on painting the trim today. Building #30- we are working on spraying the eaves today.

  • Vantage- 801, 803, 817 update

    Buildings 801 & 803 are all done except for the shutters- which we will be back to paint within the next few days. Building 817: today we are working on painting the eaves and the trim.

  • Amador- bldg 28, 29 update

    Today we are working on painting the trim on building #28 and spraying the eaves on building #29.

  • Vantage- 801, 803, 817 updates

    Bldg 801: today we are working on finishing up the touch ups to this building. Bldg 803: today we are also working on finishing up the touch ups to this building. Bldg 817: today we are spraying the stucco on the garage side of this building and we are also working on masking this building.

  • Amador- Buildings 26, 27

    Today we are working on painting the trim on Building #26 and spraying the eaves on Building #27.

  • Vantage- Buildings 803 & 817 update

    Building 803- today we are working on painting the trim and door jambs for this building. (Please remember that front doors will be done at the end of the entire project). Building 817- today we are doing some patching and we have started painting the stucco on this building.

  • Amador- Bldg 24, 25

    Today we are going to work on spraying the eaves and painting the trim on buildings 26 and 27. All of the previous buildings have been completed except for the shutters and doors.

  • Amador- 20, 21, 22, 23 update

    Bldg 20: Is all done (except for the shutters and doors) Bldg 21: We are working on painting the trim right now, then it will be all done. Bldg 22: The eaves have been sprayed but we need to do the trim. Bldg 23: We are spraying the eaves right now.

  • Vantage #803 Update

    We are working on Building 803 today. We are masking and spraying the eaves.

  • Amador Update: 17,18,19,20,21

    Buildings 17 & 18 are done (we will be back to paint the doors and shutters) Building #19- we are working on painting the trim righ now, the eaves have been sprayed. Building #20- the eaves have been sprayed, we will be working on the trim after the trim on number 19 is done. Building #21- […]

  • Vantage- Building 803 Update

    Today we are spraying the stucco on the garage side of the building. We are also still working on masking this building.

  • Amador- 17,18,19 update

    Building #17: The spraying is finished, we are currently working on painting the trim. Building #18: The spraying is finished, we need to do the trim. Building #19: We are working on spraying the eaves today.

  • Vantage 803 Bldg

    Building 803- we are masking and covering windows etc. We are also starting to spray this building today.

  • Vantage 801 update

    Building 801: the only thing left to do on this building is the trim. We will be working on the trim tomorrow.

  • Central Workshop Association

    We are excited to start the upcoming exterior painting project. A start date will be posted shortly. We will be working on this project on the weekends only, to minimize the inconvenience to the business owners/tenants.

  • Amador- Bldg 15 & 16 update

    Today we are painting the trim on building number 15 and we are spraying the eaves on building number 16.

  • Vantage-803 stucco update

    Today we are going to start spraying the stucco on building number 803.

  • Vantage- 801 update

    Today we are finishing up painting the eaves on building 801.

  • Amador- update 14, 16, 17

    Today we are working on trimming building #14 and spraying buildings 16 & 17.

  • Vantage Bldg 801 update

    Today we finished up the stucco and now are working on the eaves along the first story.

  • Amador- Bldg 14 paint update

    Today we are working on painting the eaves and trim on building number 14.

  • Amador- paint update Bldg 12 & 13

    Today we are working on painting the trim and eaves on buildings 12 and 13. As mentioned in previous posts, we will be coming back to paint the shutters and the entry doors.

  • Vantage- paint update bldg 801

    Today we are working on painting the stucco on the west side of building 801. Tomorrow we are going to work painting the stucco on the garage side of this building.

  • Vantage- Bldg 801

    We have started painting Building number 801 today.

  • Amador- 10 & 11 update

    Today we are working on painting buildings 10 and 11.

  • Vantage- paint update Bldg 801

    Building 801- color scheme #3: we will be starting to apply the paint tomorrow 9/11/12.

  • Amador- front entry door info

    Just a heads up….we will be painting the front doors at the end of the project. We will be posting a notice prior to the painting of the front doors. We usually try to paint front doors on a Saturday, when most of the homeowners can be there because the doors need to remain open […]

  • Amador- paint update Bldgs 8/9

    Today we are working on painting the trim and eaves on buildings 8 and 9. We have completed all of the trim/eaves on buildings 1 thru 8 to date. We will be coming back to finish painting the shutters and the entry doors.

  • Vantage- color scheme map

    Please see the map below with the color schemes for the association…..

  • Vantage- pressure washing update

    We are finishing up pressure washing the front entry walls right now. All of the homes on the north side of Terrace Lane have been pressure cleaned. (All of the homes on the south side of Terrace Lane will be pressure washed at a later date).

  • Amador- painting update bldgs 4 & 5

    We are currently applying the finish paint to buildings number 4 & 5. See map below-marked with yellow circles.

  • Vantage- pressure cleaning update

    We have two buildings on the North side of the street left to do- that will be completed today. Please see the map below. Also, please note- we are going to complete the North side of the street and then will start working on the units on the south side of the complex- notices will […]

  • Upland Hills Estates- fence repair

    Today we have started removing the fences at 1366/1372 Augusta, 1372/1376 Augusta. We will also be removing/replacing the fence at 1519/1525 Upland Hills Dr. South on Monday.

  • Vantage- pressure washing update

    Please see the map below that shows where we are at with the pressure washing.

  • Amador- weather delay

    Due to the rainy weather our crew is going to stop painting for the day. We will be back tomorrow, weather permitting, to resume where we left off.

  • Vantage- pressure cleaning update

    We started the high pressure cleaning today down at Building number 10. We are working from East to West.

  • Amador- paint update

    Right now our crew is working on spraying the finish on buildings two and three. (the shutters will still need to be done) So just to recap- all of the pressure cleaning, prep work and priming has been completed for the entire association. Now we are coming through to apply the finish paint.

  • Vantage- high pressure cleaning notice

    High pressure cleaning notices are being posted today for the start date of Tuesday September 4th. We are going to be posting notices for the north side of the street only.

  • Amador- paint schedule for Tuesday 9/4/12

    Our crew will start applying the paint on Tuesday September 4th. We will be working in numerical order from 1 to 33. The map that we have been using has the buildings numbered but they are small, so please call our office if you are not sure what building number you are. We will also […]

  • Amador- Holiday weekend schedule

    Our crews will not be working of this coming Saturday, Sunday and Monday. We hope that you enjoy your holiday weekend and we will be returning on Tuesday September 4th to resume with the painting project.

  • Amador- paint preparation schedule as of 8/30

    The map below shows what we have completed as far as prepping each building. We will be done with the prep work for all of the buildings tomorrow.

  • Amador prep schedule

    The map below shows the areas that have been prepped and are ready for paint. We are currently working on building number 4 which is where the arrows start. The arrows show which direction that we are working in.

  • Amador- pressure cleaning completion

    Yesterday we were able to complete the high pressure cleaning of the remaining units. Today we are high pressure cleaning the out buildings like the pool house and entry building. All of the high pressure cleaning will be finished today.

  • Amador pressure cleaning 8/28/12

    The map below has black x’s over the areas that were pressure cleaned yesterday. The red arrow marks the direct that we are working in today.

  • Amador pressure cleaning

    We started the high pressure cleaning today. We are working from Unit #9 towards unit #4. Please see the map below.

  • Amador- pressure washing notice posted 8/20/12

    Notice to Homeowner **WEATHER PERMITTING** Starting on: Monday August 27th 2012 Waddell Painting will begin high pressure washing the exteriors of the units throughout your complex. This high pressure wash is necessary before painting of the wood and metal can get started on your unit. Please note: windows may be spotted after. This is estimated […]

  • Amador- project start date****

    We will be starting the high pressure cleaning on Monday August 27th. We will be posting notices prior to the project starting. We will be high pressure cleaning the units from one end of the complex to the other. Then the prep work will start before the painting takes place. We are looking forward to […]

  • Carefree Azusa 335 Annandale

    We were able to remove, replace and paint the fence at 3354 Annandale all in one day (yesterday).

  • Carefree Azusa-335 Annandale

    A start notice was posted today…we are going to be removing and replacing the wooden fence at 335 Annandale this coming Wednesday August 8th.

  • Carefree Azusa Fence project

    Today we are finishing up the current fence project.

  • Upland Hills Estates- emergency gate & pool wrought iron painting

    Today we are working on painting the emergency gates and the pool wrought iron fencing.

  • Upland Hills Estates- wrought iron

    All of the back wrought iron fencing for the homes in the 2012 wrought iron painting phase has been completed.

  • Upland Hills Estates- Upland Hills Dr. South wrought iron

    We are still working on priming the wrought iron along Upland Hills Dr. South. (All of the prep work has been completed). We are working West to East as stated in previous posts… and are currently down by 1224. There are about 10 home left to prime. We should be starting to apply the finish […]

  • Upland Hills Estates- Upland Hills Dr. South wrought iron

    For the wrought iron fencing along the back of the homes on Upland Hills Dr. South (see job addresses in previous post) we are working from West to East. We have all of the wrought iron prepped and have primed up to 1219 (just about halfway done with the priming).

  • Carefree Azusa- 380 St. Andrews fence

    380 St. Andrews: we should be starting the removal of the fence at this address tomorrow.

  • Carefree Azusa- fences 308-364, 372&380 Pebble Beach

    Yesterday we started working on the fences at 308-364, 372 & 380 Pebble Beach. We are removing the old fences, setting new posts and then installing new fences. We should be finishing these fences this afternoon.

  • Stonewood Park- Red Curbs

    Today we are starting to paint the red curbs throughout the complex. (This project was on hold due to the hot weather).

  • Upland Hills Estates- Upland Hills Dr. South wrought iron

    Today we are working on prepping the wrought iron fences along Upland Hills Dr. South (see previous post for actual addresses). We have about 8-9 homes left to prep and then we will be painting the wrought iron.

  • Upland Hills Estates- UHDS wrought iron

    We are working on the following addresses for the painting of the back yard wrought iron: Upland Hills Dr. South (Northside): 1167, 1169, 1175, 1177, 1181, 1185, 1189, 1193, 1197, 1201, 1205, 1209, 1211, 1215, 1219, 1223, 1227, 1229, 1233, 1237, 1243, 1247, 1251, 1255, 1259, 1263, 1267, 1271, 1275, 1277, 1281, 1285, 1287, 1291, […]

  • Upland Hills Estates- painting project completion

    The painting of the houses on Winged Foot and Upland Hills Dr. South are close to completion. If you have found any touch ups  that are needed please let us know. We will be working on completing touch ups in a few days. All that is now left to do is the painting of the back wrought iron […]

  • Carefree fences 1292-1282 Pine Needles

    Today the crew is finishing up the fences at 1292-1282 Pine Needles. We are installing the lattice to match the old fences.

  • Upland Hills Estates- Upland Hills Dr. South wrought iron

    We are working on getting the wrought iron fences ready for paint. We are going to be painting the back yard wrought iron fences along the north side of the street starting at 1515/1519.

  • Phone Lines are now working

    Verizon was updating our phone and internet lines to fios. They are currently working.

  • Upland Hills Estates- Upland Hills Dr. S wrought iron fencing

    Later today we are going to start prepping the wrought iron fencing on Upland Hills Dr. South.

  • Upland Hills Estates- Upland Hills Dr. South- front doors

    Notices have been posted for the painting of the front doors this coming Saturday July 7th. If your door has had the center painted then we will just need to paint the remaining edge. Your door will need to be left open 2-3 hours to allow for drying. If you need to schedule an exact […]

  • Upland Hills Estates- Upland Hills Dr. South

    Today we are working on painting the last building, the trim.

  • Upland Hills Estates- Upland Hills Dr. South- eaves

    As of today all of the eaves have been painted in from 1515-1564 Upland Hills Dr. South.

  • Upland Hills Estates- Upland Hills Dr. South update eaves

    We have sprayed the eaves on the first five buildings and are working on spraying the eaves on the 6th  building today. There are three buildings on the north side of the street and five buildings on the south side of the street.

  • Upland Hills Estates- Upland Hills Dr. South update

    We are working on the completing the buildings on the North Side of the street first ( 1515/1519,  1529/1525.   15335/1539) Today the crew is at the second building (1529/1525) working on painting the trim.

  • Upland Hills Estates- Upland Hills Dr. South- wood repair

    As of today all of the wood removal and replacement has been completed.

  • Upland Hills Estates- Upland Hills Dr. South update

    Today we are working on painting the trim on the first building . ( 1515/1519 Upland Hills Dr. South) We are also working on spraying the eaves. We have sprayed up to and are working on the forth building.

  • Carefree Azusa- 332 Cherry Hillls fence

    332 Cherry Hills- the removal and replacement of 14’Ln. ft. of wooden fencing is now finished.

  • Carefree Azusa- 1317 TamO’Shanter fence

    1317 Tam O’Shanter- the removal and replacement of 15′ Lf Ft wooden fence is now finished.

  • Upland Hills Estates- Upland Hills Dr. South 1515/1519

    1515/1519 Upland Hills Dr. South- today we are prepping this building and spraying the eaves.

  • Upland Hills Estates- Upland Hills Dr. South- wood replacement

    Today we have a crew working on removing and replacing the damaged wood along the street.

  • Upland Hills Estates: Winged Foot patio covers

    We started prepping the homeowners patio covers who have contracted with us to have them painted. During the prep we found a lot of damaged wood.  We gave out estimates today to replace the damaged wood. We will return to finish painting those patio covers after we hear if the homeowners would like to have […]

  • Upland Hills Estates: Upland Hills Dr. South

    Yesterday and today we have been working on prepping the Upland Hills Dr. South for painting of the trim. We are also working on removing the damaged wood that is going to be replaced.

  • Carefree Azusa 1292-1282 Pine Needles

    We have been working on 1292-1282 Pine Needles back fence all this week. Monday we should be finishing up installing the top lattice.

  • Upland Hills Estates- Winged Foot patio covers

    For the homeowners who have contracted with us to paint their patio covers….we are going to start painting them tomorrow. We are posting notices today and will be posting notices throughout this week before we start on your actual unit.

  • Upland Hills Estates- Upland Hills Dr. South

    We are putting notices up today for starting to prep the homes on Upland Hills Dr. South this coming Thursday. We will be working form West to East along the street.

  • Upland Hills Estates- Winged Foot Wrought Iron

    As of today we have one house left to paint the wrought iron fencing.

  • Upland Hills Estates- Winged Foot wrought iron

    Today we also have a crew working on priming the back wrought iron fences that were prepped earlier in the week.

  • Upland Hills Estates- Winged Foot Wood Repair update

    Today we have a crew painting the new fascia that was installed yesterday. We also have a crew working on installing new siding.

  • Carefree Azusa fences starting at 1282-1292 Pine Needles

    On Monday June 18th we will be starting at 1282-1292 Pine Needles.

  • Upland Hills Estates- Winged Foot Wood Replacement

    Today we are installing the new wood along Winged Foot.

  • Upland Hills Estates- Winged Foot wood replacement

    All of the damaged wood has been removed along Winged Foot. Today we are priming the new wood and will start installing it tomorrow.

  • Carefree Azusa- fence project

    On Monday June 18th We will be starting another phase of the fencing project. We will be removing and replacing the wooden fences for the following addresses: 1317 Tam O’Shanter 302-318 Annadale 380 St. Andrews 308-364 Pebble Beach 332 Cherry Hills 1292-1282 Pine Needles. All of these homes will be receiving a notice today for […]

  • Upland Hills Estates- Winged Foot- Front Doors

    We will be out on Winged Foot on this coming Saturday to finish painting the front doors. Our crews work from 7 am to 3:30pm. Please remember that your door will need to remain open for 3-4 hours to allow for proper drying. Please contact our office if you need to schedule a specific time […]

  • Upland Hills Estates- Winged Foot wrought iron

    We are still working on prepping and painting of the back wrought iron fence today.

  • Upland Hills Estates- Winged Foot wrought iron fencing

    Today we are prepping the back wrought iron fencing along Winged Foot. Some of the guys are sanding and some are priming. We are working from East to West along the street.

  • Upland Hills Estates- front gates

    Today we are working on prepping and painting the front entry gates.

  • Upland Hills Estates- color scheme #6

    Today we are working on finishing up painting the trim in this color scheme.

  • Upland Hills Estates- color scheme #6

    Today we finished up spraying the stucco in color scheme #6. We started working on the trim today in this color scheme and will be back tomorrow to work on the trim again.

  • Upland Hills Estates- color scheme #5

    Today we finished up the trim in color scheme #5.

  • Upland Hills Estates- color scheme #6

    This morning we started spraying the stucco in this color scheme #6. We are working from West to East 1196/1198, 1242/1244, 1288/1290 Winged Foot.

  • Upland Hills Estates- color scheme #4

    Today we are working on finishing up the trim in this color scheme#4.

  • Upland Hills Estates- color scheme #5 update

    We are all done spraying the stucco throughout color scheme #5. We should be starting to work on the trim in this color scheme by the end of today.

  • Upland Hills Estates- color scheme #5 update

    We might be spraying the stucco on the first building in color scheme #5 by this afternoon, otherwise Monday morning. The address’s in this color scheme are 1188/1190,    1234/1236,    1280/1282 Winged Foot. We will be working from West to East along the street.

  • Upland Hills Estates- color scheme #4

    Color Scheme #4 update: Stucco: we are working on spraying the stucco on the last building in color scheme #4 ( 1272/1276 Winged Foot). We have completed the painting of the stucco on the first two buildings in this color scheme (1180/1182 & 1226/1228) Trim: the trim is done on the first building (1180/1182) We […]

  • Upland Hills Estates- color scheme #3 update

    We are all finished with painting in the color scheme #3 ( 1176/1178, 1218/1222, 1264/1268 Winged Foot). You will receive a notice prior to the painting of the front doors.

  • Upland Hills Estates- color scheme #4

    Color scheme#4- This morning we sprayed the stucco on 1226/1228 and we are now working on spraying the stucco at 1272/1276 right now.